YAG News Blog

Newbridge Weather

YAG Events Calendar


« April 2014 »
Mo Tu We Th Fr Sa Su
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28* Meeting and Presentation at 7:30 pm
29 30        

Snowplough 18

front-rhplough_18_9-07

This is the image most people have of Snowplough 18 when it was sat alongside Pickering Station car park for a number of years.
As can be seen here the timber work is looking worn out and a definate droop is apparent to the slope.
I decided after having a survey caried out on its condition that major repair work was required on the mainframes and to the structure of the plough slope.

The image below illustrates the condition of the lower timberwork, in some places the mainframes were so bad that you could put your hand through what should have been an oak beam 5 inches thick.

rear_buffer_beam

I contracted Rail Restorations North East of Shildon to carry out the works and so on the 21st of February 2009 plough 18 was loaded onto Duncan Milners lowloader at Newbridge yard and departed for Shildon via the A64, A1237 York Ring Rd (passing the bottom of my garden) Onto the A59 and the A1 to Shildon in a section of the former wagon works.

loading_away

crossing_the_foss

a1_northbound

arriving_shildon

offloading

From here I left number 18 in the hands of Dave Foxton and his son Steven to carry out the work.
This was to entail the separation of the body from the frame, removal of the ballast decking cast iron slabs before the body could be lifted off. Each slab is 8ft long by 6 inch by 3 inch thick and are interlocked together, with a single layer in the rear cab section and a double layer to the front, each slab had to be manhandled out of the door.
The body was removed by using the overhead crane then pushing the chassis out from under and then lowering onto stands.
The chassis was rebuilt first.
Note the new tierods and to the lower right the cast iron slabs waiting to be reinstalled.

new_frame_1

new_frame_2

new_frame_3

Once the underframe was complete attention then focused on the repair work required on the plough slope.
However prior to this the body was reunited with the frame to ensure that all bolt locations remained true and no distortion of the timbers would result.

The slope work would entail the removal of all the slope timbers and replacement in Pitch Pine as per the originals, however all the substructure framing was also in need of replacement. This kept Steven the main worker on the plough very busy making up new sections.

old_plough_slope

plough_slope

As can be seen above, the condition of the timberwork was not good by any means.
Some parts of the framing have been reused but not neccessarily in the original positions. If it was possible to reuse any of the original timber to form a smaller section then this was done.

On completion of the slope works the original work contracted for was just about complete, but I felt that the opportunity to replace some of the more awkward posts around the plough that were showing signs of rot and decay should not be missed. This considering the standard of the timber work carried out up to date.
The fitting of new corner posts and splicing in of new sections to other posts was then carried out.

new_corner_posts
Fitting of new Oak packing pieces to the buffers was one of the last jobs and the plough was then reloaded onto Duncans lowloader for return to Newbridge yard on the NYMR on the 8th of September 2010.

Compare this photo of the rear buffer beam with the one earlier.

img_3251

ready_to_leave

a1_southbound_catterick

ready_to_offload

plough_at_nbridge_11-9-10

Now all that remains to be done is for the side skirt panels to be remade, a new steel undertray to be fitted under the toe of the slope, refit the cutting edge, secure the steel sheet over the nose, refit the skylights, some attention to the doors and other body timber panels, repaint into NER Indian Red and whatever else turns up in the process.

Its all a long time since the plough arrived by rail from Gateshead back in 1975. Even then things were not as straightforward as they seem. It can just be seen that the plough is facing Whitby. It was meant to arrive facing Pickering. So it went back to Thornaby were it was turned and returned the next day.

plough_arrival

During the work carried out prior to going to shildon I recovered numerous fragments of broken wagon plates as additional ballast weight. Unfortunately none complete, these would have been from wagons being scrapped at York in 1909 when Number 18 was being built.
However I did recover some of these other plates:-

plate_1

plate_2

As part of my research into Number 18s history I have come across a number of photos of it. For a major part of its service life it was paired with Number 20 also built at York in 1909 and which also survives at Beamish although not on display. It is in the reserve store and is almost impossible to photograph.
Number 18 also featured in the British Transport film “Snowdrift at Bleath Ghyll” in the 1950s and a link is available elsewhere on this site to view this film. This was one of the rare times 18 and 20 were apart. One day they may yet be seen together again.
number_20_15-7-05_beamish

ploughs_waskerly

ploughs_51a_shed747

180862_jfm_3991

The eventual aim is to restore number 18 to a similar appearance to that of the 3rd surviving North Eastern Railway Snowplough Number 12 in the possession of the NRM and on display at its Shildon museum.

number_12_shildon_8-9-10

Plough 18 was featured in an article in Heritage Railway February 2011 issue 147 by Maurice Burns. The full version can be viewed by clicking the picture below.
As it is a scan, it may take a while to open up (860K).
mag
Update! 9th July 2011
Thought it about time that an update was given on progress.
Since the Snowplough returned from RRNE at Shildon, work has concentrated on renewing and repairing the cab bodywork planking on the east / Right hand side. Some of the lower body framing timbers needed replacing as did some of the T+G planking.
 framing_13-3-11
However it has been found possible to reuse some of the bearers in different positions and some of the planking could be reused after top and tailing, under the plough slope. New boards were purchased for the remainder and then Tongue and grooved to 6 1/4″ standard boards at Newbridge.
Lots of drilling, countersinking, screwing and filling then followed. On completion wood primer was applied with further applications of filler as required.
planking_13-5-11
New side skirt panels had to be produced out of 1 1/4″ T+G. They get heavy I can tell you. I even drafted in assistance from home in the form of my wife Christine.
chris_painting_18-6-11
For the first time during sanding off I found some original lettering. Dating from the 50s
br_lettering
I know you cannot make it out here but it details Number and Allocation to West Auckland as in this photo below but on the opposite side.
18_west_auckland
During this time Nick Hutchinson was busy cutting steel sheet, welding and drilling to produce a new toe sheet. This sheet extends back underneath and required a lot of fiddling about to suit the angled bolts from the top sheet.
plough_toe_11-3-11
Nick Carter had taken on the task of masterminding the repaint with occaisional assistance from his neighbour Dave. He also has managed to involve the home authorities in this case recording his tracing work on Plough 12 at the NRM Shildon to try and identify the font in use for the lettering.
nick_carter_shildon_8-6-11
The first transformation appeared when panels started changing colour to Pink. Well the undercoat was available and originally was the undercoat for West Yorkshire PTE Red. This was followed by an intermediate coat of Red Oxide.
first_intermediate_coat_18-6-11
A new member of the team appeared in the form of Phil Baker who has taken on the task of rebuilding the 2 cab doors.
As can be seen Phil has found a spot out of the way on the deck of the plate wagon to carry out the repair work to the doors.
This mainly comprises of stripping the old planking off, cleaning out the inner frame, replacing any rotten frame members, making sure the droplightswork and waxing the slides, refixing the frame then shaping and fixing new T+G planking.
 img_3943
door_repair_8-7-11
Painting has now progressed to the application of the first coat of top coat Indian Red. Currently the rear end and the East side body are painted. Stencils have been delivered which will be used for Nick to apply the lettering detailing the plough’s allocation to Bishop Auckland.
top_coat_8-7-11
More progress is expected to be made next week 15th July.
On Wed 24th August number 18 was loaded away to Kirkby Stephen for the Stainmore 150th event over the Bank Holiday weekend. Moved by Moveright. It was also its first day in the sun for a while all the better to see the paint in the best light.
As part of the loading process the lorry had to go into the quarry to turn round once the plough had been loaded.
front-rh
img_4286
On its return from Kirkby Stephen Plough 18 has gone on its travels again. This time to the far North.
Grosmont. It has now completed its first return journey on the NYMR taking 36 years to do it.
Is this also a first for a GWR loco having an independant Snowplough attached?
7822andplough-003-nc
Created and Hosted by the York Area Group.
website security