Newbridge Pit Road

Newbridge Pit Road.

Today 20-3-12 the state of play was that rail has been replaced to a new alignment off the pit.

It now waits for shuttering to be constructed then concrete pouring before any more rail is laid. Access required for ready mix lorry. After which a plain line will be laid to reconnect to the yard trackwork. Once this is finalised we will then position a recovered turnout and reconnect the shed side siding.

Newbridge pit road

Newbridge pit road

 

 

 

 

 

 

 

 

 

 

 

 


This was the state of play Sunday afternoon 1-4-12 and no the date has nothing to do with it.

Next question “Where do we put the points for the siding?”

pit-road-1-4-12