Ballast Regulator Gallery
It is the intention to create a stock of photos illustrating the different purposes and equipment on each machine to explain what it does and how. Click on a picture to see it full size and scroll down the picture to read about the picture details.
Below is the Regulator.
Ex Grant Rail at Scunthorpe GR5044.
Reg 7 5 6 1
Reg 2 7 5 6 1
Reg setting up 1
The purpose of regulating the ballast is to ensure all sleeper bays are full both before and after tamping.
This is achieved by use of adjustable blades that are used to move ballast around or remove excess ballast to the sides.
This is then followed up with a brush pass to sweep the sleeper tops clear.
This enables accurate examination of sleepers, their fastenings and rail condition.
It also improves the stability of the track by increasing the resistance to the effects of hot weather.
reg dash L 1 BJB 20-3-12
The machine can be driven from either side so controls are mirrored.
However the controls for the blades only relate to either left or right.
So either 2 operators or keep swapping seats.
Reg dash R 1
Reg dash 1 BJB 20-3-12
The machine can be driven from either side so controls are mirrored.
However the controls for the blades only relate to either left or right.
So either 2 operators or keep swapping seats
Reg Levisham clearance b 1
However we have managed to trim off some of the protruding parts and have managed this enough to allow the machine to pass through from Pickering to Grosmont Tunnel with some limitations as to direction it faces and which line it must use.
Note the amount the side blade overhangs the platform edge at Levisham.
Reg Levisham clearance a 1
Reg post stone tip 1
A Stone train has deposited a load of stone in the 4ft piled to about 30cm / 1ft above rail level. It requires spreading to either side of the rails filling in any empty bays as it is moved.
The stone level must be reduced to below top rail level to allow the tamper to work without interference to the lining wire under the tamper.
Reg setting blades 1
The blades in the middle are hydraulically controlled and can be moved to a variety of positions to move the stone around depending on site requirements.
During any regulator operations it is advisable to walk through the site first and identify any site restrictions or hazards marking with paint if required.
These obstacles may range from S+T cables crossing the track to buried bridge girders and station platforms.
If needed ask for someone to guide you past an obstacle.
Reg ploughing b 1
Reg ploughing a 1
Most stone is pushed to the side, however some can be allowed to pass through a gap in the blades if needed. Forming a small potato row in the 4ft.
Nick brushing b 1 BJB 20-3-12
Reg brushing a 1 BJB 20-3-12
Reg brush box 1 BJB 20-3-12
The box is fitted with rubber shrouds around the bottom of the box which are meant to catch any flying stone but some stone does get past and can fly for some distance.
Clip cleaners are fitted to knock stone off rail fastenings. These are actually short pieces of Steel wire rope and are positioned around the rail profile.
Reg brushed track a 1 BJB 20-3-12
Note all sleepers and fastenings visible.
All bays filled and a good neat shoulder to the sides.
Reg brushing c 1 BJB 20-3-12
Reg brushing b 1 BJB 20-3-12
Note the amount of stones left on the rail top these need to be cleared off before work is completed and the line reopened for traffic.
Reg working a 1
This is normal operating practice when in working mode.
Reg going home 1
Reg 2006 Side plough a 1
N Carter 2006
Reg 2006 side plough b 1
N Carter 2006
Reg 2006 Side plough c 1
N Carter 2006
Reg 2006 Side plough d 1
N Carter 2006


